IMPLEMENTATION STAGES OF THE MUNICIPAL WASTE
THERMAL TREATMENT PLANT (EfWP) IN POZNAŃ
8 IV 2013 |
Signing of the Public-Private Partnership (PPP) agreement between the city of Poznań and SITA Zielona Energia |
17 X 2013 |
Obtaining the revised Environmental Decision |
18 XI 2013 |
Obtaining the revised Location Decision |
6 II 2014 |
Obtaining the final construction permits |
18 IV 2014 |
Commencement of construction works |
22 V 2014 |
The official ceremony of the "First Shovel" for the construction of the EfWP |
IX 2014 |
Commencement of the waste bunker construction and the “emergence" of the first installation wall above the surface of the ground |
V-X 2015 |
Installation of technological equipment (including boiler, grate, fume treatment system, installation of the slag adjustment and turbine with a generator) |
III-X 2016 |
start-up of the installation |
XI 2016 |
Putting the installation into use (43 months from the signing of the agreement) |
2041 |
The EfWP shall be transferred to the city of Poznań (termination of the PPP agreement after 25 years from the launch of the installation) |